Customization Service

From requirement analysis to installation and commissioning — a four-step process with a written scope at every gate.

Customization Service

Industry Challenges

Non-standard cartons

Shapes, board grades or sizes outside the standard catalogue range.

Line interface constraints

Existing conveyors, takt and controls that a standard machine does not match.

Site and environment limits

Footprint, ceiling height, dust, temperature or wash-down requirements.

How ZRAY Solves It

Customization is engineering work before it is manufacturing: we confirm the cartons, the takt and the interfaces in writing, then design, build, test and commission against that agreed scope.

Key Capabilities

4 steps
Requirement analysis to commissioning
8 items
Customizable dimensions

Scope of Supply

Deliverables Requirement confirmation, selection proposal, layout drawing, electrical interface plan, quotation.
Validation Pre-shipment trial run on your cartons; FAT with remote witnessing or free sample testing.

Projected results

4 steps
Fixed process with documented outputs
100 %
Pre-shipment trial run on customer cartons

Related Videos

Delivery and assurance

Standard machines ship in 45–60 days. Customized lines: 90–120 days after drawing approval. Every unit runs on representative cartons before it leaves the plant.

Lead time 90–120 days after drawing approval for customized lines.

Get a solution proposal

Send us your carton sizes and line takt — we reply with a machine selection and layout.